BAM Weekly Working Group February 13th, 2023

From Bay Area Mesh
Jump to navigation Jump to search

Attendees

  • Mathison Ott
  • Dave Dornlas
  • Christiaan Adams
  • Tim Wilkinson

Notes by

  • Tim Wilkinson

Major Discussions Topics

  • ORCA
    • Summary of the work done at ORCA last Friday. Trees around antenna pole cleared, loose cabling tied up (temporarily) and path towards airport opened up.
    • Discussions of future mesh needs - update nodes, dish to Wolfback, Internet link
  • Sunol Ridge
    • Rescheduled (again) to 18th Feb. Mathison and Tim doing the install.
  • San Bruno
    • Camera for potential installation at San Bruno has now arrived. Still need to find out if we can actually put on there or not.