Attendees

  • Dave Dornlas
  • Jim Moss
  • Tim Wilkinson
  • Mathison Ott
  • Scott Nacey
  • John Swallow
  • Chris Adams

Notes by

  • Tim Wilkinson

Major Discussions Topics

  • PBX
    • Mathison has setup a new PBX as the old one had stopped working. People can transfer their numbers over or get a new number (or several)
  • Speaking at West Valley
    • Jim is schedule to present on the 14th
  • Company in Emeryville
    • Legal stuff has been finalized and the install can now proceeed
    • Currently waiting to visit the site's roof to find what we need for the final install (hopefully this week)
  • San Bruno Mtn (Building 4)
    • With the installation of new mounting hardware at Building 4, Dennis is good for us to install at the site.
    • Need to get a good link there as we can't see our current nodes at Building 7. Running a link from Fish Ranch is probably the way to go.
  • Stanford Radio Club
    • Rachel from SCARES recently gate a talk there and there is interest in installing nodes at their site.
  • Black Mountain Problems
    • Jim is working on why the radio at Black Mountain no longers works well. This appears to coincide with the upgrade to 3.23.4.0 but the root cause remains difficult to nail down. Work in progress.
  • John Cornell
    • No news on connecting John's set of Laorinda nodes to the switch at Fish Ranch
  • San Bruno Mtn <-> Fish Ranch
    • We're using a radio from Matt to get traffic from Fish Ranch to San Bruno but the channel we're on seems problematic. Trying to get information from Matt.