BAM Weekly Working Group March 11th, 2024

From Bay Area Mesh
Revision as of 12:45, 11 March 2024 by Kn6plv (talk | contribs) (Created page with "=== Attendees === * Christiaan Adams * Tim Wilkinson * John Swallow === Notes by === * Tim Wilkinson === Major Discussions Topics === * Scale21 ** Linux + AREDN show in Pasadena, LA this weekend ** Will be providing local mesh info for conference visitors and encouraging participation. * Update on failed backbone ** Backbone failed this morning when the connection between Sunol Ridge and Mt Allison failed. ** Should have re-routed around fault but didn't. ** Need to...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Attendees

  • Christiaan Adams
  • Tim Wilkinson
  • John Swallow

Notes by

  • Tim Wilkinson

Major Discussions Topics

  • Scale21
    • Linux + AREDN show in Pasadena, LA this weekend
    • Will be providing local mesh info for conference visitors and encouraging participation.
  • Update on failed backbone
    • Backbone failed this morning when the connection between Sunol Ridge and Mt Allison failed.
    • Should have re-routed around fault but didn't.
    • Need to simulate the failure and debug
  • Fish Ranch batteries
    • Chris replaced failing batteries at Fish Ranch.
  • General backbone updates
    • New sector at Wolfback. Provides much better connectivity to CCCC. Offers potential for more connections in the future.
    • 10GHz connection between Hurricane Electric and Mount Allison in place after failure to connect to FS8. Needs improved power solution at Allison.